Thursday 25 February 2016

When the BDA rejected for plan approval that the builder cannot escape from their liability to complete the project if the adjacent land has been approved for the same builder. 
                                                        
The Hon'ble National Commission has clinched the above title and interpreted that no builder can escape from their liability once they have acted upon by promising to perform the contract if the alternative remedy was available for the builder to complete their obligation within the purview of the law. 

The factual matrix of the case that the builder had been noticed by legal experts due to non-execution of Sale Deed on behalf of the several Villa buyers because of the land for the phase in which villas were allotted to the complainants was comprised in survey Nos.112/P and 89/P of Boganahalli village and the building plans for the said phase comprising 40 villas were rejected by Bangalore Development Authority vide letter dated 11-09-2006. A perusal of the aforesaid letter would show that the building plan for construction of residential complex on the aforesaid land were rejected solely on the ground that a major portion of the said land was reserved for the proposed road and a portion was reserved for residential purpose in RCDP – 1995

The complaints have been resisted by the opposite parties primarily on the ground that the allotment to the complainants was made subject to approval of the plans by the concerned authorities and the plans submitted by them to Bangalore Development Authority were not approved by the said authority, on the ground that in the Comprehensive Development Plan (RCDP-1995) substantial portion of the land on which villas in question were to be constructed was reserved for a road. It is further stated in the reply that as per the current master plan (revised master plan-2015) which came into force on 25-06-2007 the land in question is classified as industrial and residential use is permitted only as an ancillary use in the said hi-tech zone. According to the opposite parties, the contract between the parties was a contingent contract, performance of which has become impossible. It is further stated in the reply that way back in 2007 the complainants were informed that they could take refund of their money along with interest.

The learned counsel for the opposite parties, in support of his contention that the forum cannot direct execution of a contract which had become impossible to perform even if such a performance becomes possible at a later date referred to the decision of the Hon’ble Supreme Court in K. Narendra Vs. Riviera Apartments (P) Ltd., 1999 (5) SCC 77; 2001 (5) SCC (101), Her Highness Maharani Shantidevi P. Gaikwad Vs. Savjibhai Haribhai Patel & Ors. He also referred to the decisions of the Hon’ble Supreme Court in 1973 (2) SCC 746, Har Prasad Choubey Vs. Union of India & Anr. and 1969 1 SCR 65, Boothalinga Agencies Vs. V.T.C. Poriaswanmi Nadar. He also placed reliance upon the decision of Delhi High Court in AIR 1986 Del 158, Punj Sons Pvt. Ltd. Vs. Union of India. However, none of these judgments would apply considering that we are proceeding on the assumption that on account of the refusal of the Bangalore Development Authority to sanction the plans for construction of villas on the land comprised in survey No.89 and 112, the contract between the parties had become void in terms of Section 56 of the Contract Act and considering the stand taken by the opposite parties that no villa is available with them for providing to the complainants we do not propose to direct the opposite parties to either construct villas or to provide readymade villas to the complainants. But It transpired during the course of hearing that after denying the villas booked by the complainants to them, the opposite parties got approved building plans for construction of villas on the land adjoining the land comprised in survey No.112 & 89. Therefore, the BDA has only rejected to issue plan approval for comprised survey Nos.112/P and 89/P.

Even if we proceed on the assumption that on account of refusal of Bangalore Development Authority to sanction building plans on the entire land comprised in survey No.112 and 89, the contract between the parties to sell villas in question to the complainants had become impossible to perform, the complainants are entitled to compensation in terms of Section 56 of the Contract Act since in our view, the opposite parties knew or with reasonable diligence might have known but the complainants did not know that the villas in question could not have been constructed on the land comprised in survey No.112 and 89. Besides their right under the provisions of Contract Act the complainants are also entitled to suitable compensation under the provisions of Consumer Protection Act on account of deficiency/negligence in the services rendered to them by the opposite parties. The Forum confirmed that the builder has to pay compensation to the complainants as per the terms of the order.


Please see, for Complete Judgement Study,In Smt. Anuradha Maganthi & another Vs M/s. A Developers NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI CONSUMER COMPLAINT NO.99 OF 2007 and Judgement Pronounced on 28.11.2014

No comments:

Post a Comment